September 2018


  • Abatement is 95% complete for the entire Community School building.
  • New kitchen’s existing concrete pad has been sawcut to accommodate drains, electrical, etc.
  • Trusses for the new kitchen roof are on order.
  • New kitchen equipment is on order.
  • West wing of the Community School is demolished.
  • Underground steam tunnels are being demolished.
  • Existing HVAC systems have been removed from the building and will be reused by the district.
  • OPA portables construction complete, awaiting final inspections by the City of Sequim.

Capital Project Levy Deconstruction Progression Panorama