December 2018

Vanir presented an update to the SSD School Board on December 17, 2018. You can view their presentation here.

  • Deconstruction of the Community School is at 100% completion
  • Haul away of deconstruction materials is at 100% completion
  • Kitchen roof is complete, interior construction underway including ducting, electrical and plumbing
  • Insulation is completed
  • Doors and windows are installed
  • Air units are installed on the roof
  • CCPUD has installed a new kitchen transformer
  • Water and sewer have been connected to the city lines on Fir Street
  • Drywall has been delivered
  • New fire alarm systems for OPA and the OPA gym to be installed, beginning in January