November 2018

• Deconstruction of the Community School is at approximately 95% completion.
• Haul away of deconstruction materials is ongoing, and at about 60% completion.
• Roof trusses have been delivered, and kitchen roof is under construction.
• Sawcutting in new kitchen floor and installation of utility components complete, concrete poured.
• Utility connections are underway with assistance from the City of Sequim and CCPUD.
• Quotations have been received for new fire alarm systems for OPA and the OPA gym.

Capital Project Levy Deconstruction SiteCapital Project Levy Deconstruction Site
Capital Project Levy Deconstruction Site