Current Capital Projects 2021-2024

   Welcome
Welcome!

Capital Project Levy Timeline of Events and Milestones:


2021
  • February 9: Capital Levy Passed
  • August 5: Construction Manager hired for Capital Project Levy
  • November 9: Bid Loft Multi-Purpose Room & Elevator Projects (Project No. 1001 & 1002)
2022
  • April 4-8: Helen Haller Portable Fire Alarm (Project No. 1003)
  • April 22: First Levy Fund Assessment by DOR
  • June 16: First Levy Funding Received
  • June 20 - August 30: Fiber Optic Infrastructure Installation (Project No. 2001)
  • July 9 - August 15: Phone System Equipment Replacement (Project No. 2002)
  • August 8 - September 15: Replace Olympic Peninsula Academy and Sequim Middle School flat roofing (Project No. 1004)
  • September 14: Board votes to reorganize levy priority to address safety concerns, vote on camera installation in December.
  • October 17: Second Levy Fund Assessment
  • October 18: Track Investigation and Assessment
  • October 21: Select Design firm for HVAC Replacement at Olympic Peninsula Academy (Project No. 1006)
  • October 26: Select Design firm for HVAC Replacement at Sequim High School (Project No. 1005)
  • December 18 - January 14: Exterior Surveillance Camera Installation (Project No. 2007)
2023
  • February 9: Initial Planning for Olympic Peninsula Academy Fencing
  • March 21: Select Fencing Contractor for OPA (Project No. 1008)
  • April 20: Helen Haller Fire Alarm Solicitation. Project Halted. Rebid Summer 2024
  • May 12 - June14: Olympic Peninsula Academy Fencing Installation
  • May 20: Replacement Equipment for Olympic Peninsula Academy ordered
  • June14 - August: Sequim High School Gym Floor Replacement (Project No. 1016)
  • June 24: Wireless Access Point, Clock, and Intercom Cabling (Project No. 2011)