April 2018

  • The best suited design option has been chosen for the new central kitchen.   It is now transitioning from schematic design to permit and contract document design.
  • Kitchen equipment and layout needs for the district kitchen staff have been reviewed and incorporated into the design.
  • Documents to write specifications and create a formal bid for a demolition contractor are under review. 
  • Temporary fencing has been placed around the new Central Kitchen site and Community School for safety. 
  • A Capital Project Levy Ground Breaking Ceremony date has been set for May 18th.